Redpath bores record breaking hole at Macassa gold mine

Redpath Mining‘s raiseboring division has completed another record breaking hole last week at Kirkland Lake Gold’s (TSX:KL) Macassa gold mine. At a […]
Redpath bored the longest raise in the Americas at the Macassa gold mine. Credit: Redpath Raiseboring.
[caption id="attachment_1003748100" align="alignnone" width="604"] Redpath bored the longest raise in the Americas at the Macassa gold mine. Credit: Redpath Raiseboring.[/caption]

Redpath Mining's raiseboring division has completed another record breaking hole last week at Kirkland Lake Gold’s (TSX:KL) Macassa gold mine. At a length of 1,010 metres, this raise became the longest raise bored hole ever accomplished in the Northern Hemisphere and all of the Americas. This concludes the first of the planned twin, 365-cm diameter ventilation raises extending from surface down to 5617 level.

The hole was accomplished in two stages with two machines drilling concurrently; a Redbore 70 underground and a Redbore 90EX on surface, completing individual ventilation raises of 660 metres and 1,010 metres respectively. The Redbore series raise bore machines were designed and manufactured in-house by Redpath in North Bay, Ont.

The milestone occurred merely three months after Redpath broke another record at Niobec niobium mine in Quebec. That raise was the largest ever completed in the Americas and the Northern Hemisphere, and the third biggest globally.

“Like with our Niobec project, the Macassa record is the result of an outstanding team effort that started in 2019. Months of preparation went into engineering design, procurement and preparation of the equipment. Throughout the project, the operational execution, technical support and project management and controls were exceptional. We’ve established a strong partnership with Kirkland Lake Gold’s project team and the support they’ve provided throughout the project has been tremendous. Most importantly, this important milestone was completed without any lost time injuries or major incidents”, said Johan Davel, general manager of Redpath Raiseboring.

“The completion of this raise marks a major milestone for Kirkland Lake Gold as we continue major ventilation upgrades at Macassa. The experience and expertise of Redpath Raiseboring was a major factor in the success of the project to date and we look forward to continued rewarding collaboration with Redpath at Macassa”, said James Gagne, manager of mining at Kirkland Lake Gold.

Preparations have started to carry out the second raise bore hole at Macassa, with equally successful results expected.

Learn more at www.RedpathMining.com/services/raiseboring.

Comments

Your email address will not be published. Required fields are marked *

Apr 08 2024 - Apr 09 2024
Apr 15 2024 - Apr 16 2024
Apr 16 2024 - Apr 16 2024
Apr 17 2024 - Apr 18 2024