New Gold (TSX: NGD) (NYSE American: NGD) has extended the life of its New Afton and Rainy River mines with new technical incorporating growth projects the company has invested in over recent years.
New Afton's copper and gold reserves increased by 15% and 13%, respectively, compared to the end of 2024. The increase is attributed to a 27% rise in tonnage at the C-Zone and the introduction of the East Extension Zone, where the copper and gold grades are more than double that of the C-Zone.
New Gold said the new mineral reserves came at no additional cost and are expected to support a one-year extension to 2031. The Canadian miner also pointed to opportunities to further extend the block-caving operation in British Columbia from the prospective K-Zone, HW Zone and D-Zone.
At Rainy River, the open pit -- initially set to reach full depletion in early 2025 -- has been extended to 2028 after incorporating the optimized Phase 5 pit design, which would push the processing of low-grade stockpile into the future and keep the mill running at full capacity until 2029.
Despite a 2% decrease in open pit reserves at Rainy River, the company has reported a 76% increase in gold resources, which it said presents an opportunity to further extend the mine, and growth in underground reserves to approximately 1.34 million oz.
CEO Patrick Godin said the life-of-mine plans "successfully outline New Gold's strong production profile with reducing costs, strong free cash flow generation and increasing net asset value, while also highlighting exciting opportunities to build on over the longer-term."
Building on the mine extensions, New Gold has presented a three-year outlook that illustrates higher production and cost reduction leading to significant cash flow generation.
In 2025, the Toronto-based miner expects its consolidated gold production to increase by 16% to 325,000-365,000 oz., driven mainly by the improved production profile at Rainy River. Over the next three years, the mine located 65 kilometres northwest of Fort Frances, Ontario, is expected to have average production of 300,000 oz. per year.
Meanwhile, its copper production is expected to be in line with 2024 at 50-60 million lb., as the ramp-up in New Afton's C-Zone throughput is offset by planned lower grades from both the exhaustion of the B3 cave and first draw bells from C-Zone.
All-in sustaining costs are expected to decrease by $215/oz., or 17% compared to the 2024 midpoint of guidance, to between $1,025-$1,125/oz., resulting from higher production and lower operating costs from the New Afton C-Zone crusher and conveyor system and as the Rainy River Phase 4 strip ratio decreases.
Total capital is expected to be $270-$315 million, in-line with the 2024 guidance range, as New Afton C-Zone and Rainy River underground continue to ramp up and as development starts at the New Afton East Extension and Rainy River Phase 5 expansions.
"In 2024, the company reached a free cash flow inflection point and 2025 will continue to build on that. This year, we expect to see the value from the significant investments made in recent years on our growth projects through increased production, decreasing costs, and substantial free cash flow generation," stated Godin.
In 2026 and 2027, consolidated gold production is projected to increase even higher at 55% (435,000-490,000 oz.) and 37% (375,000-445,000 oz.) respectively, compared to 298,303 oz. in 2024. Again, the increases will be driven by the improved production profiles at both Rainy River and New Afton as growth projects are completed and ramped up in the near-term.
Copper production is also expected to continue to increase, with 2027 copper production pegged between 95-115 million lb., approximately 94% higher than 2024, driven by increased grade and throughput from New Afton's C-Zone.
All-in sustaining costs are expected to decrease significantly by approximately 70% compared to the 2024 midpoint of guidance to between $400-$500/oz., coinciding with the anticipated completion of the Rainy River Phase 5 expansion in 2026. The 2027 total capital is expected to be $70-$95 million, also a significant drop from 2024.
The higher production, lower costs, and lower capital spend over the 2025-2027 period are expected to drive increasing margins and generate significant free cash flow for the company, said New Gold.
Shares of New Gold were down 2.6% to C$4.17 apiece by midday Thursday, for a market capitalization of C$3.3 billion.