Thor expects first gold pour at Segilola by end of July

The mining fleet is now fully commissioned, and production is expected to quickly ramp up to its design capacity.
Casting of leaching tank. Credit: Thor Explorations Ltd.

Topics

Commodities

Regions

Tags

Companies

Thor Explorations Ltd. (TSXV: THX) continues to make progress in bringing its wholly owned Segilola gold project in Nigeria towards production, and the company is now expecting its first gold pour by the end of this month.

On Monday, Thor announced the start of the commissioning of its gold processing plant at Segilola following the successful turning of the mills.

Remaining work on the project is focused primarily on the gold room, elution and electrowinning circuit, power connection, instrumentation and control installations, the company added.

The process plant is being commissioned in phases, with commissioning having already started at the power plant. Commissioning of the SAG & ball mills and the crushing section will follow.

Thereafter, commissioning will continue with the remaining areas of the process plant.

Mining is currently underway, with 700,000 tonnes of waste mined and 30,000 tonnes of ore stockpiled in preparation for process plant commissioning. The pit is fully prepared for mining operations, with pre-strip nearing completion.

The mining fleet is now fully commissioned, and production is expected to quickly ramp up to its design capacity, Thor stated in Monday's news release.

All the necessary permits are in place and blasting operations have started as the company moves into the harder transitional and fresh ore zones.

Shares of Thor Explorations were down 9.0% by 11:30 a.m. in Toronto. The Africa-focused gold miner has a market capitalization of C$186.9 million.

This story originally appeared on www.Mining.com.

Comments

Your email address will not be published. Required fields are marked *

Dec 01 2024 - Dec 02 2024
Dec 03 2024 - Dec 05 2024